WORLD-GENERATION NOVEMBER/DECEMBER 2016
22
FERC 827 RULING
CONTINUED FROM PAGE 14
can cause system voltage to sag, preventing
real power to flow through the lines. In
extreme cases, insufficient reactive power
resources can result in voltage collapse and
even power outages. Because of this,
utilities and grid operators have taken
careful measures to regulate reactive power
so they can deliver nominal voltage under
varying load conditions. This is in part the
reason why we have strict interconnection
requirements for both synchronous and
non-synchronous generators, so that each
power facility can contribute to the reactive
power supply on the utility grid.
REACTIVE POWER COMPENSATION
TECHNOLOGIES
To control reactive power on the utility
grid or when interconnecting generation
facilities, system operators and developers
have a variety of technologies that can help
implement their control strategies. From
smart inverters and advanced wind
converters to Static Var Compensators and
STATCOMS (Static Synchronous
Compensators), the location of the
renewable facility and the condition of the
surrounding electrical network will by and
large dictate the solution required to help
meet the local grid codes and this new
FERC 827 requirement.
TECHNOLOGY IN ACTION: STATCOMS
Although many modern wind turbines
are able to fulfill voltage control
requirements by themselves, wind parks as
a whole sometimes still need additional
reactive power compensation to cover the
balance of plant. When Type-I and Type-II
wind farms in particular are in operation,
dynamic VAR compensation devices can be
useful to meet the grid requirements. One
of the devices which can enable this is the
Static Synchronous Compensator
(STATCOM).
STATCOM is one of the members of
the FACTS (Flexible AC Transmission
System) family. It is a low voltage power
electronic based device which acts as a
source or sink for the reactive power. The
major components of a STATCOM are a
DC capacitor, a power converter, filters and
a step up transformer connecting it to the
grid.
A STATCOM will be able to quickly
respond to grid events (with a response
time of one to two cycles), providing
dynamic voltage control, regardless of the
wind farm layout. Even on weak grids, the
STATCOM device has the capability to
control reactive power and ultimately
enhancing the power output of the wind
farm.
As our society move towards cleaner
sources of power such as wind and solar,
maintaining the integrity of the electrical
grid will continue to be a priority.
Regulatory bodies such as FERC have
issues several orders to help ensure safe
and reliable connection of non-synchronous
generators (i.e. wind and solar) to the
transmission network.
As October 14, 2016, the new FERC
ruling requires newly interconnecting non-
synchronous generators to meet dynamic
reactive power requirements. However, for
already existing facilities that are making
upgrades and making new
interconnections, such requests will be
exempt from these requirements as it
“could expose entities with existing power
purchase agreements to unforeseen
expenses.” This can be subject to change if
the transmission provider’s System Impact
Study shows that meeting the reactive
power requirement is necessary to ensure
safety or reliability.
For the rest of the newly
interconnecting non-synchronous
generators, they will be required to meet
the reactive power requirements at the high
side of the generator substation, and not
the Point of Interconnection. This means
that in most cases advanced wind turbine
converters can provide enough reactive
power control, so that no further
technology is needed. However, in areas
where the grid is weak, or the surrounding
load is variable, additional dynamic reactive
power compensation is required.
PERSPECTIVE
operation, and a 7 kV line was tripped off.
But, there was so much solar on the line, it
remained energized beyond the six-cycle
time limit, and six more feeders tripped off
as a result.
In both of these cases, one problem
looms: lack of control. Much of that problem
stems from centralized control that takes too
long to really react to rapidly-changing
conditions from intermittent generation.
THE OPEN FIELD MESSAGE BUS APPROACH
A few years ago, engineers at Duke
Energy were trying to coordinate solar and
storage installations. To that end, they
clocked the round trip from sensors on an
inverter to the head-end system, through
the computation cycle and then back to the
inverter. It took some 40 seconds. This is
what got Duke started down the path of
OpenFMB
TM
, a reference architecture that
provides a framework for distributed
intelligence.
Working with Duke and other industry
players, SGIP’s OpenFMB
TM
working group
shepherded this architecture through the
standards process. It was ratified as a
standard by the North American Energy
Standards Board (NAESB) in March of 2016
and, at SGIP’s 2016 Grid Modernization
Summit held in Washington, DC November,
we launched a collaborative website where
people can access the OpenFMB
TM
code
itself.
OpenFMB
TM
supports grid-edge
coordination of distributed energy resources
and the grid itself because it facilitates local
data exchange on a circuit segment, which
enables decision making without centralized
system control. That’s crucial because
Supervisory Control and Data Acquisition
(SCADA) systems typically collect grid-
status data every four or five seconds, and
that’s just not fast enough when you have a
protective scheme that must operate in six
cycles.
BACK ON CAMPUS
CONTINUED FROM PAGE 19